top of page

Cork Harbour Horizontal Directional Drilling

Project Location:

Cork Harbour, Ireland

Client Name:

Ervia / Irish Water

Project Description:

OCU was contracted to design and install twin 1,025 metre lengths of 500mm Diameter SDR-9 PE100 Foul Main under Cork Harbour using Horizontal Directional Drilling (HDD). A discharge chamber was constructed on the west shore, with tie-in works to connect to the existing network. Under a local road closure, the pipe was moved 1.5 kilometres from the fabrication area to the drill exit using 144 rollers, 3 cradles, 4 excavator clamps, and a 50-tonne hydraulic pusher.

Key Stats:

• 114 meters of 16-inch surface casing

• 400 tonne Mega Rig mobilised

5 Months

Duration

Challenge

• Cork Lower Harbour is designated as a Special Area of Conservation, a Special Protection Area, and a Natural Heritage Area

• To comply with the Urban Wastewater Treatment Directive, Irish Water and Cork County Council transferred 20,000 wheelie waste bins daily to a new treatment facility to prevent raw sewage discharging into Cork Harbour

Solution

• Redesign the bore path, adjust the reception shaft, and alter the pipeline fabrication to minimise risk

• Ecological and archaeological surveys, infrastructure inspections, riverbed dive survey, and noise and vibration assessments were conducted

• Boreholes were drilled at entry and exit to assess contamination risks, and a water supply bore was established for the HDD operation

• A bridge was built over the Glen Burn at the exit for access

Outcome

• The project exceeded 80,000 manhours with no reportable accidents or incidents

• OCU hit every KPI during these works and exceeded 98% on the client’s monthly audits

• Longest horizontal directional drills in Ireland and completed in a continuous effort of over 24 hours

• Our teams successfully pulled a pipe over 1.3 kilometres under the estuary

• Close liaison with the full project team and the local community to guarantee safety

bottom of page