Ferrybridge 150MW BESS Project
.jpg)
Project Location:
Ferrybridge
Client Name:
Scottish and Southern Energy Renewables Ltd
Project Description:
OCU were awarded the contract by Scottish and Southern Energy Renewables Ltd for the Design, Construction, Commissioning and Handover of the 132kV/33kV Electrical Infrastructure and Substation Plant and Control Systems. We also provided all Civil Engineering works and installation of the Battery Containers located at the Ferrybridge Power Station.
OCU are the appointed Principal Contractor responsible for the co-ordination of the works with the Client and their nominated Battery Technology Supplier.
Key Stats:
Development of 150MW/300MWh Battery Energy Storage System (BESS)
Point of connection at 132kV
Reuse and Recycling of over 6000m3 of existing materials
Building Information Modelling (BIM) utilised
New Battery technology and container installation
18 Months
Duration
Challenge
Working in close proximity to National Grid Assets and Overhead Lines (OHL).
Designed to meet client's requirements within a tight footprint.
Demolition of redundant SSE Assets.
Ecology.
On-time delivery of key technologies i.e. Battery cells.
Programme critical milestones to meet.
Interface with multiple Stakeholders.
Solution
On-time delivery supported by the wide range of our in-house services.
Worked closely with our client and their other partners to ensure timetable and milestones met.
Installation of:
180MVA, 132/33/33Kv ONAN/ONAF, OLTC Transformer
145kV, Three Phase Dead Tank Outdoor Circuit Breaker
Surge arrestors and Disconnector within the National Grid compound
Disconnector within the BESS compound
40KA HAM CT/VT & HAM metering
33kV Earthing transformers and BESS auxiliary transformers
BESS LVAC Boards 400V AC
Two-story switch house with integral spares room
Outcome
Programme is being delivered on-time and on-budget.
Zero harm record.
Full regulatory and legislation compliance achieved, with no environmental incidents.
Critical dates and milestones achieved throughout programme.
Implementation of control measures to ensure non-interruption to the National Grid Network Operations during construction.
OCU are providing a maintenance contract now the park has commenced commercial operations.
Objective of 10% Biodiversity Net Gain has been successfully achieved.
