top of page

Mill Hill, Longforgen

Project Location:

Mill Hill, Longforgen

Client Name:

Scottish and Southern Electricity Networks (SSEN)

Project Description:

OCU was engaged to deliver an upgrade to the electrical infrastructure at Mill Hill, Longforgan. This included installing new 11kV wood poles, overhead switchgear, and a third wire to supply a new 200kVA transformer. Our teams carried out detailed site assessments and created an outage plan to minimise disruption. The project formed part of a new connection request from an SSEN customer, requiring a three-phase supply and transformer upgrade, to support the installation of new solar and ground source heat pumps.

Key Stats:

  • Full access agreements secured

  • Site-specific RAMS collated

  • 5-day outage plan developed

5 Days

Duration

Challenge

  • Multiple landowners were identified during the access stage, which extended the time required to secure permissions.

  • Two sections of the works presented challenging access conditions, requiring additional resources to complete the works safely.

  • Access issues posed a risk to completing the project within the approved 5-day outage plan.

Solution

  • Carried out a site meeting with both the landowners and SSEN

  • Discussed the areas that required additional work for safe access

  • Provided a marked plan identifying tree-cutting areas from access points to poles

  • Final plan carefully developed, balancing SSEN’s customer requirements and compliance with Scottish Woodlands regulations

Outcome

  • Despite access challenges and tight planning parameters, the project was successfully delivered within the approved 5-day outage window

  • The replacement of 13 existing poles with upgraded 11kV wooden poles significantly improved the structural reliability and future resilience of the overhead line network

  • Installing 1.6km of high-performance conductor increased the line’s capacity to accommodate the new transformer and low-carbon technologies

bottom of page