top of page

Penwortham BESS - Howick Cross

Project Location:

Preston, Lancashire

Client Name:

Gresham House

Challenge

  • Inadequate design from previous contractor.

  • Long lead time materials were not ordered by previous contractor.

  • Liaising with DNO to ensure compliance.

  • Finding defective equipment on commission and removing and rectifying DTCB.

  • Implementation with “loop in loop out” on DNO (ENWL) live incoming circuit.

  • Our commission team highlighted numerous issues with defective equipment from previous contractor.

Solution

  • Redesign of controls package.

  • Building confidence with the DNO to facilitate the relationship that assisted in energisation.

  • Worked with service partners GE and internal resource OCU Hornbill to rectify defected dead tank circuit breaker.

  • Providing additional testing at DNO request in order to build confidence that site was ready to energise.

  • Our construction team rewired and engineered up to 90% of site.

  • We worked closely with DNO and the main contractor to rectify issues to ensure engineering deadlines were met.

Project Description:

OCU were brought in to take over rectification of the design, finalising construction and completing the energisation of site following the former supplier's liquidation.

Key Stats:

  • 132kv ICP connection

  • 15 x PCS

  • Loop in loop out onto existing critical DNO circuit

1 Year

Duration

Outcome

  • Project energised on time for client.

  • Minimised the delay damages due to failure of former contractor.

  • Worked effectively with DNO to close out remaining issues.

  • Awarded additional take over works at Melksham due to IPE performance.

bottom of page