top of page
6W2A1946 - Large.jpg

Case Studies

We are committed to leading the way in utilities and energy transition contracting; our mission is to innovate and deliver sustainability. OCU’s passion for addressing complex challenges brings new standards of growth in our people and capabilities.

Peterhead Substation

Under an NEC3 subcontract, we built a 2000m² GIS Substation, two transformer buildings, a 210m x 150m platform, reinforced structures, improved access, and installed underground cabling with GRP covers.

Neilston Grid Stability Facility

NEC4 Option A contract involved the construction of a 653m² portal frame for a Synchronous Condenser, with 8500m² platform, 1km access road, fencing and earthing - providing robust, secure foundations for long-term operation.

Pitkevey BESS Fife, Scotland

The project covered full BoP works for a 50MW battery storage site in Fife, including access roads, drainage, switchrooms, 33kV cabling, MV transformers, BESS units, and 2km of DNO cabling over sensitive terrain.

Cork Harbour Horizontal Directional Drilling

OCU was contracted to design and install twin 1,025 metre lengths of 500mm Diameter SDR-9 PE100 Foul Main under Cork Harbour using Horizontal Directional Drilling (HDD).

Dee-crossing Connah's Key

OCU was awarded the Dee Crossing contract, located in Connah’s Quay. Our teams designed and installed two 860m-long barrier pipelines under the River Dee using Horizontal Directional Drilling (HDD). 

Ray Wind Farm 20MW BESS Project

This 20MW Battery Energy Storage System (BESS) project was constructed at Ray Wind Farm approximately 5km south of the village of Otterburn in Northumberland.

Pitkevy 40 MW BESS Project

Our teams delivered the Civil and Electrical works associated with a new 50MW Battery Energy Storage System (BESS).

Jamesfield 49MW BESS Project

Our teams provided the Civil and Electrical works associated with a new 49MW Battery Energy Storage System (BESS).

Humber Cluster Energy Saving Campaign

ABP identified a number of Transformer Assets that are progressing in age and have a considerable number of losses when they are transforming the High Voltage Network down to the localised Low Voltage requirement.

Ferrybridge 150MW BESS Project

OCU were awarded the contract by Scottish and Southern Energy Renewables Ltd for the Design, Construction, Commissioning and Handover of the 132kV/33kV Electrical Infrastructure and Substation Plant and Control Systems.

Capenhurst 100MW BESS Project

Capenhurst is a 100MW Battery Energy Storage System (BESS) connected to the National Grid (NGET) at 275kV.

Vodafone Fibre Call Out

OCU is contracted by Vodafone to deliver fibre and civils call out services on a 24/7/365 basis throughout England and Wales.

Penwortham BESS - Howick Cross

OCU were brought in to take over rectification of the design, finalising construction and completing the energisation of site following the former supplier's liquidation.

NEOS Fibre Maintenance - UK Wide

OCU holds the repair and maintenance agreement with NEOS throughout England. We provide all fibre associated works including, Highways, PIA, confined spaces, roof top, and overhead cables.

Modular Storm Tanks - SW Water

OCU took on the emergency job of the installation of several modular storm tanks at 3 different live site locations to meet key WINEP dates for SWW compliance to the EA for 2024 in a 12-week window as PC and PD for SWW at their request in Devon.

Lumen Fibre Maintenance

OCU is the road network maintenance provider for Lumen. Our teams are responsible for repairs across COLT Neo’s (Lumen’s 500km fibre network) both proactively and reactively.

Filter Case Studies By:

bottom of page